COYLTON ENERGY LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Coylton 275kV Greener Grid Park | Coylton 275kV substation | Storage | 450 | 30 Apr 2026 Past date +2 mo | Gate 2 | Scoping |
Recent changes
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageConnection point changed from Coylton 275/132kV to Coylton 275kV substation
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageStage 1: Connection date moved from 28 Feb 2026 to 18 May 2026 (+3 months)+3 mo
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageStage 1: Given a Gate 2 connection offerGate 2
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageConnection point changed from Coylton 275/33kV Substation to Coylton 275/132kV
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageRestructured from 1 stage (150 MW from 30 May 2025) to 3 stages (50 MW from 28 Feb 2026, 100 MW from 30 Apr 2026, 300 MW from 30 Oct 2037). First connection date +9 months+9 mo
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageConnection date moved from 30 Jul 2025 to 30 May 2025 (−2 months)−2 mo
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageConnection point changed from Coylton GSP to Coylton 275/33kV Substation
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageCapacity changed from 49.9 MW to 150 MW
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageConnection date moved from 25 Oct 2024 to 30 Jul 2025 (+9 months)+9 mo
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageTechnology changed from Storage, Reactive compensation to Storage
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageCustomer changed from STATKRAFT UK LTD to COYLTON ENERGY LIMITED
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageConnection date moved from 30 Apr 2025 to 25 Oct 2024 (−6 months)−6 mo
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageSubstation name updated in the register (from Coylton to Coylton GSP)
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageRenamed from Coylton 275kV Synchronous Compensation and BESS
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageTechnology changed from Storage to Storage, Reactive compensation
- Coylton 275kV Greener Grid ParkSouth Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?