Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / North Scotland

Pentland Floating Offshore Wind Farm

HIGHLAND WIND LIMITED at Pentland Floating Offshore Wind Farm 132/66kV substation

Connection date
3 Apr 2028 +5 months since 9 Dec
Gate
Gate 2
Status
Consents Approved
Planning consent
Granted 28 Jun 2023
Marine Scotland, reference NA · Source: REPD
Contract for Difference
Allocation Round 7
Technology
Offshore wind
Total capacity
100 MW
Connected now
0 MW
Still to connect
100 MW
Transmission owner
SSEN Transmission (SHET)
Agreement type
Direct Connection
Region
North Scotland
Project number
PRO-001472
In the register since
June 2021

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 18 Sep 2026 register
    Connection date moved from 31 Oct 2027 to 3 Apr 2028 (+5 months)
  • 18 Sep 2026 register
    Status changed from Scoping to Consents Approved
  • 18 Sep 2026 register
    Given a Gate 2 connection offer
  • 30 Sep 2025 register
    Connection point changed from OWF-100 Substation to Pentland Floating Offshore Wind Farm 132/66kV substation
  • 28 Mar 2025 register
    Connection date moved from 31 Aug 2025 to 31 Oct 2027 (+26 months)
  • 28 Nov 2023 register
    Renamed from OWF-100
  • 23 Dec 2022 register
    Substation name updated in the register (from OWF-100 to OWF-100 Substation)
  • 29 Jun 2021 register
    Added to the register

Also at Pentland Floating Offshore Wind Farm 132/66kV substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO

Planning consent

The planning decision or stage for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition, with the planning authority and its reference. QueueWatch matched the project to that record. NESO’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this project, from DESNZ’s Renewable Energy Planning Database (REPD), July 2026 edition. QueueWatch matched the project to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.