HIGHLAND WIND LIMITED
Customer named in the TEC register
1project in the register
100 MWstill to connect
100 MWof that with Gate 2 offers
0 MWconnected now
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Pentland Floating Offshore Wind Farm | Pentland Floating Offshore Wind Farm 132/66kV substation | Offshore wind | 100 | 3 Apr 2028 +5 mo | Gate 2 | Consented |
Recent changes
- Pentland Floating Offshore Wind FarmNorth Scotland, Offshore windConnection date moved from 31 Oct 2027 to 3 Apr 2028 (+5 months)+5 mo
- Pentland Floating Offshore Wind FarmNorth Scotland, Offshore windStatus changed from Scoping to Consented
- Pentland Floating Offshore Wind FarmNorth Scotland, Offshore windGiven a Gate 2 connection offerGate 2
QueueQuant
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose