QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Gretna Synchronous Compensation

GRETNA GRID SERVICES LIMITED at Gretna 400/132kV

Connection date
Connected
Gate
Not stated
Status
Built
Technology
Reactive compensation
Total capacity
0 MW
Connected now
0 MW
Still to connect
0 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-001444
In the register since
November 2021

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 31 Oct 2025 register
    Connection date removed (was 15 Jun 2025)
  • 31 Oct 2025 register
    Status changed from Consents Approved to Built
  • 27 Jun 2025 register
    Connection date moved from 30 Sep 2024 to 15 Jun 2025 (+9 months)
  • 27 Sep 2024 register
    Connection point changed from Gretna 400kV Substation to Gretna 400/132kV
  • 29 Jul 2022 register
    Substation name updated in the register (from Gretna to Gretna 400kV Substation)
  • 31 May 2022 register
    Customer changed from WP GRID SERVICES 3 LIMITED to GRETNA GRID SERVICES LIMITED
  • 31 Dec 2021 register
    Status changed from Scoping to Consents Approved
  • 30 Nov 2021 register
    Added to the register

Also at Gretna 400/132kV

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO