GRETNA GRID SERVICES LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Gretna Synchronous Compensation | Gretna 400/132kV | Other | 0 | Connected | Not stated | Built |
Recent changes
- Gretna Synchronous CompensationSouth Scotland, OtherConnection date removed (was 15 Jun 2025)
- Gretna Synchronous CompensationSouth Scotland, OtherStatus changed from Consents Approved to Built
- Gretna Synchronous CompensationSouth Scotland, OtherConnection date moved from 30 Sep 2024 to 15 Jun 2025 (+9 months)+9 mo
- Gretna Synchronous CompensationSouth Scotland, OtherConnection point changed from Gretna 400kV Substation to Gretna 400/132kV
- Gretna Synchronous CompensationSouth Scotland, OtherSubstation name updated in the register (from Gretna to Gretna 400kV Substation)
- Gretna Synchronous CompensationSouth Scotland, OtherCustomer changed from WP GRID SERVICES 3 LIMITED to GRETNA GRID SERVICES LIMITED
- Gretna Synchronous CompensationSouth Scotland, OtherStatus changed from Scoping to Consents Approved
- Gretna Synchronous CompensationSouth Scotland, OtherAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?