Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland

Neilston 132

NEILSTON ENERGY LIMITED at Neilston 132kV Substation

Connection date
Increase at an existing station: +100 MW from 31 Oct 2025
Gate
Not stated
Status
Built
Technology
Storage
Total capacity
150 MW
Connected now
50 MW
Still to connect
100 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-001343
In the register since
April 2021

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 19 Dec 2025 register
    Renamed from Neilston 132kV Greener Grid Park
  • 19 Dec 2025 register
    Connection point changed from Neilston 400/275/132kV to Neilston 132kV Substation
  • 31 Oct 2025 register
    Restructured from 2 stages (50 MW from 31 May 2024, 100 MW from 31 Oct 2025) to 1 stage (50 MW connected + 100 MW from 31 Oct 2025). First connection date +17 months
  • 30 May 2025 register
    Stage 1: Status changed from Scoping to Consents Approved
  • 30 May 2025 register
    Stage 1: Technology changed from Storage, Reactive compensation to Storage
  • 30 May 2025 register
    Stage 2: Status changed from Scoping to Awaiting Consents
  • 30 May 2025 register
    Stage 2: Technology changed from Storage, Reactive compensation to Storage
  • 27 Sep 2024 register
    Connection point changed from Neilston 132kV Substation to Neilston 400/275/132kV
  • 27 Aug 2024 register
    Customer changed from STATKRAFT UK LTD to Neilston Energy Limited
  • 29 Sep 2023 register
    Restructured from 1 stage (49.9 MW from 1 Jul 2023) to 2 stages (50 MW from 31 May 2024, 100 MW from 31 Oct 2025). First connection date +11 months
  • 23 Dec 2022 register
    Substation name updated in the register (from Neilston 132kV to Neilston 132kV Substation)
  • 30 Mar 2022 register
    Renamed from Neilston 132kV
  • 28 Jan 2022 register
    Capacity changed from 16.5 MW to 49.9 MW
  • 28 Jan 2022 register
    Connection date moved from 30 Apr 2023 to 1 Jul 2023 (+2 months)
  • 30 Nov 2021 register
    Technology changed from Storage to Storage, Reactive compensation
  • 31 Aug 2021 register
    Connection date moved from 16 Dec 2022 to 30 Apr 2023 (+4 months)
  • 30 Apr 2021 register
    Added to the register

Also at Neilston 132kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO