Neilston 132
- Connection date
- Increase at an existing station: +100 MW from 31 Oct 2025
- Gate
- Not stated
- Status
- Built
- Technology
- Storage
- Total capacity
- 150 MW
- Connected now
- 50 MW
- Still to connect
- 100 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001343
- In the register since
- April 2021
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 19 Dec 2025 registerRenamed from Neilston 132kV Greener Grid Park
- 19 Dec 2025 registerConnection point changed from Neilston 400/275/132kV to Neilston 132kV Substation
- 31 Oct 2025 registerRestructured from 2 stages (50 MW from 31 May 2024, 100 MW from 31 Oct 2025) to 1 stage (50 MW connected + 100 MW from 31 Oct 2025). First connection date +17 months
- 30 May 2025 registerStage 1: Status changed from Scoping to Consents Approved
- 30 May 2025 registerStage 1: Technology changed from Storage, Reactive compensation to Storage
- 30 May 2025 registerStage 2: Status changed from Scoping to Awaiting Consents
- 30 May 2025 registerStage 2: Technology changed from Storage, Reactive compensation to Storage
- 27 Sep 2024 registerConnection point changed from Neilston 132kV Substation to Neilston 400/275/132kV
- 27 Aug 2024 registerCustomer changed from STATKRAFT UK LTD to Neilston Energy Limited
- 29 Sep 2023 registerRestructured from 1 stage (49.9 MW from 1 Jul 2023) to 2 stages (50 MW from 31 May 2024, 100 MW from 31 Oct 2025). First connection date +11 months
- 23 Dec 2022 registerSubstation name updated in the register (from Neilston 132kV to Neilston 132kV Substation)
- 30 Mar 2022 registerRenamed from Neilston 132kV
- 28 Jan 2022 registerCapacity changed from 16.5 MW to 49.9 MW
- 28 Jan 2022 registerConnection date moved from 30 Apr 2023 to 1 Jul 2023 (+2 months)
- 30 Nov 2021 registerTechnology changed from Storage to Storage, Reactive compensation
- 31 Aug 2021 registerConnection date moved from 16 Dec 2022 to 30 Apr 2023 (+4 months)
- 30 Apr 2021 registerAdded to the register
Also at Neilston 132kV Substation
Substation viewNo other projects in the register at this connection point.