NEILSTON ENERGY LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Neilston 132 | Neilston 132kV Substation | Storage | 100 | 31 Oct 2025 Past date | Not stated | Built |
Recent changes
- Neilston 132South Scotland, StorageRenamed from Neilston 132kV Greener Grid Park
- Neilston 132South Scotland, StorageConnection point changed from Neilston 400/275/132kV to Neilston 132kV Substation
- Neilston 132South Scotland, StorageRestructured from 2 stages (50 MW from 31 May 2024, 100 MW from 31 Oct 2025) to 1 stage (50 MW connected + 100 MW from 31 Oct 2025). First connection date +17 months+17 mo
- Neilston 132South Scotland, StorageStage 1: Status changed from Scoping to Consents Approved
- Neilston 132South Scotland, StorageStage 1: Technology changed from Storage, Reactive compensation to Storage
- Neilston 132South Scotland, StorageStage 2: Status changed from Scoping to Awaiting Consents
- Neilston 132South Scotland, StorageStage 2: Technology changed from Storage, Reactive compensation to Storage
- Neilston 132South Scotland, StorageConnection point changed from Neilston 132kV Substation to Neilston 400/275/132kV
- Neilston 132South Scotland, StorageCustomer changed from STATKRAFT UK LTD to Neilston Energy Limited
- Neilston 132South Scotland, StorageRestructured from 1 stage (49.9 MW from 1 Jul 2023) to 2 stages (50 MW from 31 May 2024, 100 MW from 31 Oct 2025). First connection date +11 months+11 mo
- Neilston 132South Scotland, StorageSubstation name updated in the register (from Neilston 132kV to Neilston 132kV Substation)
- Neilston 132South Scotland, StorageRenamed from Neilston 132kV
- Neilston 132South Scotland, StorageCapacity changed from 16.5 MW to 49.9 MW
- Neilston 132South Scotland, StorageConnection date moved from 30 Apr 2023 to 1 Jul 2023 (+2 months)+2 mo
- Neilston 132South Scotland, StorageTechnology changed from Storage to Storage, Reactive compensation
- Neilston 132South Scotland, StorageConnection date moved from 16 Dec 2022 to 30 Apr 2023 (+4 months)+4 mo
- Neilston 132South Scotland, StorageAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?