Quantans Hill Wind Farm
- Connection date
- 2 Jul 2029
- Gate
- Not stated
- Status
- Scoping
- Technology
- Onshore wind
- Total capacity
- 95 MW
- Connected now
- 0 MW
- Still to connect
- 95 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-001247
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 24 Dec 2024 registerConnection date moved from 30 Apr 2027 to 2 Jul 2029 (+26 months)
- 28 Feb 2023 registerCapacity changed from 126 MW to 95 MW
- 23 Dec 2022 registerConnection point changed from Quantans Hill 132kV Substantion to Quantans Hill 132kV Substation
Also at Quantans Hill 132kV Substation
Substation view1 other project, 145 MW still to connect at this substation in total.