QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales
Connection date
30 Oct 2030
Gate
Not stated
Status
Scoping
Technology
Storage + Solar
Total capacity
57 MW
Connected now
49.9 MW
Still to connect
7.1 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001114
In the register since
January 2021 or earlier

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Stages

StageConnected MWAdds MWCumulative MWDateGateStatus
149.9049.9NoneNot statedBuilt
207.15730 Oct 2030Not statedScoping

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 29 Jul 2025 register
    Customer changed from PIVOTED POWER LLP to HOLLYGREEN ENERGYFARM LIMITED
  • 27 Jun 2025 register
    Restructured from 1 stage (49.9 MW connected) to 2 stages (7.1 MW from 30 Oct 2030, 49.9 MW connected)
  • 28 Feb 2025 register
    Customer changed from HOLLYGREEN ENERGYFARM LIMITED to PIVOTED POWER LLP
  • 31 Jan 2025 register
    Customer changed from PIVOTED POWER LLP to HOLLYGREEN ENERGYFARM LIMITED
  • 26 Nov 2024 register
    49.9 MW now connected
  • 26 Nov 2024 register
    Status changed from Under Construction/Commissioning to Built
  • 28 Jun 2024 register
    Connection date moved from 12 Dec 2023 to 31 Oct 2022 (−13 months)
  • 26 Apr 2024 register
    Connection date moved from 31 Oct 2022 to 12 Dec 2023 (+13 months)
  • 28 Jul 2023 register
    Status changed from Awaiting Consents to Under Construction/Commissioning
  • 23 Dec 2022 register
    Substation name updated in the register (from Walpole 400kV to Walpole 400kV Substation)

Also at Walpole 400kV substations

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO