QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.
Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / England and Wales

Wymondley Solar Farm

AGR SOLAR 4 LIMITED at Wymondley 400/33kV Substation

Connection date
30 May 2027 +19 months since 9 Dec
Gate
Gate 2
Status
Consents Approved
Technology
Storage + Solar
Total capacity
50 MW
Connected now
0 MW
Still to connect
50 MW
Transmission owner
National Grid Electricity Transmission (NGET)
Agreement type
Direct Connection
Region
England and Wales
Project number
PRO-001105
In the register since
March 2021

What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 16 Oct 2026 register
    Given a Gate 2 connection offer
  • 18 Sep 2026 register
    Connection point changed from Wymondley 400kV Substation to Wymondley 400/33kV Substation
  • 18 Sep 2026 register
    Connection date moved from 31 Oct 2025 to 30 May 2027 (+19 months)
  • 28 Mar 2025 register
    Connection date moved from 30 Jun 2024 to 31 Oct 2025 (+16 months)
  • 26 Apr 2024 register
    Status changed from Scoping to Consents Approved
  • 28 Jul 2023 register
    Connection point changed from Wymondley GSP to Wymondley 400kV Substation
  • 23 Dec 2022 register
    Substation name updated in the register (from Wymondley to Wymondley GSP)
  • 25 Feb 2022 register
    Connection date moved from 1 Jul 2023 to 30 Jun 2024 (+12 months)
  • 30 Jul 2021 register
    Technology changed from Solar to Storage, Solar
  • 30 Jul 2021 register
    Stage removed (0 MW)
  • 29 Jun 2021 register
    New stage added (0 MW)
  • 28 May 2021 register
    Stage removed (0 MW)
  • 30 Mar 2021 register
    Added to the register

Also at Wymondley 400/33kV Substation

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO