AGR SOLAR 4 LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Wymondley Solar Farm | Wymondley 400/33kV Substation | Storage with solar or wind | 50 | 30 May 2027 +19 mo | Gate 2 | Consents Approved |
Recent changes
- Wymondley Solar FarmEngland and Wales, Storage with solar or windGiven a Gate 2 connection offerGate 2
- Wymondley Solar FarmEngland and Wales, Storage with solar or windConnection point changed from Wymondley 400kV Substation to Wymondley 400/33kV Substation
- Wymondley Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 31 Oct 2025 to 30 May 2027 (+19 months)+19 mo
- Wymondley Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 30 Jun 2024 to 31 Oct 2025 (+16 months)+16 mo
- Wymondley Solar FarmEngland and Wales, Storage with solar or windStatus changed from Scoping to Consents Approved
- Wymondley Solar FarmEngland and Wales, Storage with solar or windConnection point changed from Wymondley GSP to Wymondley 400kV Substation
- Wymondley Solar FarmEngland and Wales, Storage with solar or windSubstation name updated in the register (from Wymondley to Wymondley GSP)
- Wymondley Solar FarmEngland and Wales, Storage with solar or windConnection date moved from 1 Jul 2023 to 30 Jun 2024 (+12 months)+12 mo
- Wymondley Solar FarmEngland and Wales, Storage with solar or windTechnology changed from Solar to Storage, Solar
- Wymondley Solar FarmEngland and Wales, Storage with solar or windStage removed (0 MW)
- Wymondley Solar FarmEngland and Wales, Storage with solar or windNew stage added (0 MW)
- Wymondley Solar FarmEngland and Wales, Storage with solar or windStage removed (0 MW)
- Wymondley Solar FarmEngland and Wales, Storage with solar or windAdded to the registerNew
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?