Braintree (Tertiary)
- Connection date
- 30 Oct 2026
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 49.9 MW
- Connected now
- 0 MW
- Still to connect
- 49.9 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-001043
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerStatus changed from Awaiting Consents to Consents Approved
- 24 Dec 2024 registerTechnology changed from Solar to Storage, Solar
- 30 Jul 2024 registerConnection date moved from 30 Jul 2025 to 30 Oct 2026 (+15 months)
- 30 May 2023 registerStatus changed from Scoping to Awaiting Consents
- 28 Feb 2023 registerConnection point changed from Braintree GSP to Braintree 400kV Substation
- 30 Mar 2022 registerSubstation name updated in the register (from Braintree to Braintree GSP)
- 25 Feb 2022 registerConnection date moved from 30 Oct 2025 to 30 Jul 2025 (−3 months)
- 28 Jan 2022 registerConnection date moved from 30 Jul 2025 to 30 Oct 2025 (+3 months)
Also at Braintree 400kV Substation
Substation view4 other projects, 1.7 GW still to connect at this substation in total.
- BraintreePIVOTED POWER LLP, Storage with solar or wind, Gate 2May 202757 MW
- Bulls Lodge Farm 2548 UK INVESTMENT HOLDINGS LIMITED, Storage with solar or wind, Gate 1Mar 2033350 MW
- Bulls Lodge Farm548 UK INVESTMENT HOLDINGS LIMITED, Storage with solar or wind, Gate 1Apr 2033200 MW
- BraintreeBraintree 10 Renewables Limited, Storage with solar or wind, Gate 1Oct 20341 GW