Kincardine Battery Storage Facility
KINCARDINE GRID 1 LTD at Fife Grid Services Facility 275kV Substation
- Connection date
- 15 Dec 2028 +32 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 200 MW
- Connected now
- 0 MW
- Still to connect
- 200 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000856
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 5 Jun 2026 registerConnection date moved from 31 Mar 2026 to 15 Dec 2028 (+32 months)
- 5 Jun 2026 registerGiven a Gate 2 connection offer
- 27 Mar 2026 registerCustomer changed from SPECTRUMRESERVE LTD to KINCARDINE GRID 1 LTD
- 29 Apr 2025 registerConnection date moved from 12 Apr 2024 to 31 Mar 2026 (+24 months)
- 28 Sep 2021 registerConnection point changed from Kincardine to Fife Grid Services Facility 275kV Substation
- 28 Sep 2021 registerConnection date moved from 28 Jun 2024 to 12 Apr 2024 (−3 months)
Also at Fife Grid Services Facility 275kV Substation
Substation view2 other projects, 400 MW still to connect at this substation in total.