Fife Grid Services
KINCARDINE GRID 3 LTD at Fife Grid Services Facility 275kV Substation
- Connection date
- 30 Jul 2027 (0 MW)
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Reactive compensation
- Total capacity
- 0 MW
- Connected now
- 0 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000453
- In the register since
- November 2021
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Oct 2026 registerMarked as Gate 1
- 30 Jan 2026 registerCustomer changed from BLUEGRIDPOWER LTD to KINCARDINE GRID 3 LTD
- 21 Nov 2025 registerConnection date moved from 12 Apr 2024 to 30 Jul 2027 (+40 months)
- 30 Nov 2021 registerAdded to the register
Also at Fife Grid Services Facility 275kV Substation
Substation view2 other projects, 400 MW still to connect at this substation in total.