Delays and exits in the transmission queue since 2021How often connection dates move, and how many projects leave the queue. Gate 2 in the transmission queueHow much of the queue has a Gate 2 offer, and what it did to connection dates. The battery queue and CMP470’s commitment feeHow far the battery queue sits above the line that would switch CMP470’s commitment fee off. Changes of customer in the transmission queueHow often connection agreements move between companies, and how those projects fared. Do projects connect on time?How late stages have connected against their connection date in the register. Which connection dates slip least?Which connection dates are pushed back least, allowing for how far ahead they are. Grid outages and the connections due by 2030How many of their planned outages the transmission owners carry out, against the connections due by 2030.

More analyses are on the way.

Transmission / Projects / South Scotland
Connection date
1 Aug 2028
Gate
Not stated
Status
Awaiting Consents
Technology
Onshore wind
Total capacity
96 MW
Connected now
0 MW
Still to connect
96 MW
Transmission owner
SP Energy Networks (SPT)
Agreement type
Direct Connection
Region
South Scotland
Project number
PRO-000565
In the register since
January 2021 or earlier

Change history

Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.

  • 18 Sep 2026 register
    Status changed from Scoping to Awaiting Consents
  • 27 Jun 2025 register
    Connection date moved from 14 Jul 2027 to 1 Aug 2028 (+13 months)
  • 30 May 2025 register
    Substation name updated in the register (from Daer Windfarm 132/33kV to Daer Wind Farm 132/33kV)
  • 27 Sep 2024 register
    Substation name updated in the register (from Daer Wind Farm Substation to Daer Windfarm 132/33kV)
  • 23 Dec 2022 register
    Substation name updated in the register (from Daer Wind Farm to Daer Wind Farm Substation)
  • 30 Jul 2021 register
    Customer changed from RWE RENEWABLES UK DEVELOPMENTS LIMITED to RWE RENEWABLES UK ONSHORE WIND LIMITED

Also at Daer Wind Farm 132/33kV

Substation view

No other projects in the register at this connection point.

Status definitions (NESO)

Scoping: NESO is not aware that a planning application has been made.

Awaiting Consents: NESO is aware, or the customer has told it, that a planning application has been made.

Consents Approved: NESO is aware, or the customer has told it, that the planning application has been approved.

Terminated: used by NESO only in its register of 30 April 2021, for two projects that left the register the next month.

These statuses are NESO’s, not QueueWatch’s, and NESO describes them as “as far as we are aware”, so a project may be further along than its status shows.

Source: NESO