- Connection date
- 1 Dec 2030
- Gate
- Gate 1
- Status
- Scoping
- Technology
- Storage + Onshore wind
- Total capacity
- 167 MW
- Connected now
- 106 MW
- Still to connect
- 61 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000515
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 106 | 0 | 106 | None | Not stated | Built |
| 2 | 0 | 61 | 167 | 1 Dec 2030 | Gate 1 | Scoping |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 20 Oct 2026 registerStage 2: Status changed from Consents Approved to Scoping
- 20 Oct 2026 registerStage 2: Marked as Gate 1
- 30 Sep 2025 registerRestructured from 1 stage (106 MW from 30 Apr 2024) to 2 stages (61 MW from 1 Dec 2030, 106 MW connected). First connection date +79 months
- 29 Aug 2025 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 31 Oct 2023 registerCustomer changed from LIMEKILN GRID LIMITED to Limekiln Extension Limited
- 28 Sep 2021 registerRestructured from 2 stages (84 MW from 1 Oct 2022, 22 MW from 31 Oct 2027) to 1 stage (106 MW from 30 Apr 2024). First connection date +19 months
- 26 Feb 2021 registerStage 1: Connection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)
Also at Limekilns 132/33kV substation
Substation viewNo other projects in the register at this connection point.