BERWICK BANK C LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Berwick Bank Offshore Wind Farm C | Blyth 400kV Substation | Offshore wind | 1,800 | 30 Nov 2029 | Not stated | Scoping |
Recent changes
- Berwick Bank Offshore Wind Farm CEngland and Wales, Offshore windConnection date moved from 31 Oct 2031 to 30 Nov 2029 (−23 months)−23 mo
- Berwick Bank Offshore Wind Farm CEngland and Wales, Offshore windConnection point changed from Seagreen Platform 3A & 3B to Blyth 400kV Substation
- Berwick Bank Offshore Wind Farm CEngland and Wales, Offshore windRenamed from Seagreen Phase 3
- Berwick Bank Offshore Wind Farm CEngland and Wales, Offshore windCapacity changed from 1,850 MW to 1,800 MW
- Berwick Bank Offshore Wind Farm CEngland and Wales, Offshore windConnection date moved from 14 Nov 2036 to 31 Oct 2031 (−60 months)−60 mo
- Berwick Bank Offshore Wind Farm CEngland and Wales, Offshore windCustomer changed from MARR BANK WIND LIMITED to BERWICK BANK C LIMITED
- Berwick Bank Offshore Wind Farm CEngland and Wales, Offshore windTransmission owner changed from SPT to NGET
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?