Shepherds Rig Wind Farm
- Connection date
- 30 May 2030 +70 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 21 Aug 2023
Scottish Government (S36), reference ECU00000735 · Source: REPD - Technology
- Onshore wind
- Total capacity
- 84.6 MW
- Connected now
- 0 MW
- Still to connect
- 84.6 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000511
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 23 Jun 2026 registerConnection point changed from Shepherds Rig Wind Farm 132kV Substation to Shepards Rig 132/33kV
- 23 Jun 2026 registerConnection date moved from 30 Jul 2024 to 30 May 2030 (+70 months)
- 23 Jun 2026 registerStatus changed from Scoping to Consents Approved
- 23 Jun 2026 registerGiven a Gate 2 connection offer
- 23 Dec 2022 registerSubstation name updated in the register (from Shepherds Rig Wind Farm 132kV to Shepherds Rig Wind Farm 132kV Substation)
Also at Shepards Rig 132/33kV
Substation viewNo other projects in the register at this connection point.