SETT WIND DEVELOPMENT LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Shepherds Rig Wind Farm | Shepards Rig 132/33kV | Onshore wind | 84.6 | 30 May 2030 +70 mo | Gate 2 | Consents Approved |
Recent changes
- Shepherds Rig Wind FarmSouth Scotland, Onshore windConnection point changed from Shepherds Rig Wind Farm 132kV Substation to Shepards Rig 132/33kV
- Shepherds Rig Wind FarmSouth Scotland, Onshore windConnection date moved from 30 Jul 2024 to 30 May 2030 (+70 months)+70 mo
- Shepherds Rig Wind FarmSouth Scotland, Onshore windStatus changed from Scoping to Consents Approved
- Shepherds Rig Wind FarmSouth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
- Shepherds Rig Wind FarmSouth Scotland, Onshore windSubstation name updated in the register (from Shepherds Rig Wind Farm 132kV to Shepherds Rig Wind Farm 132kV Substation)
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?