Walpole 2 (tertiary)
- Connection date
- 31 Oct 2027
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage + Solar
- Total capacity
- 100 MW
- Connected now
- 0 MW
- Still to connect
- 100 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000505
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Apr 2026 registerConnection point changed from Walpole 400kV Substation to Walpole 132kV Substation
- 30 Sep 2025 registerStatus changed from Scoping to Consents Approved
- 24 Dec 2024 registerConnection date moved from 31 Oct 2024 to 31 Oct 2027 (+36 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Walpole 400kV to Walpole 400kV Substation)
- 29 Jul 2022 registerRestructured from 2 stages (100 MW from 31 Oct 2024, 0 MW from 31 Oct 2025) to 1 stage (100 MW from 31 Oct 2024)
- 30 Jun 2022 registerStage 1: Capacity changed from 49.9 MW to 100 MW
- 30 Jun 2022 registerStage 1: Connection date moved from 1 Jul 2023 to 31 Oct 2024 (+16 months)
- 30 Jun 2022 registerStage 2: Capacity changed from 7.1 MW to 0 MW
- 30 Jun 2022 registerStage 2: Connection date moved from 31 Oct 2023 to 31 Oct 2025 (+24 months)
- 26 Feb 2021 registerStage 1: Connection date moved from 7 Jan 2023 to 1 Jul 2023 (+6 months)
Also at Walpole 132kV Substation
Substation view3 other projects, 100 MW still to connect at this substation in total.