Thurrock Power Station
THURROCK FLEXIBLE GENERATION LIMITED at Tilbury 275kV Substation
- Connection date
- Increase at an existing station: +375 MW from 30 Jun 2026 +8 months since 9 Dec
- Gate
- Gate 2
- Status
- Built
- Planning consent
- Granted 16 Feb 2022
Thurrock Flexible Generation Plant (EN010092) · Source: Planning Inspectorate - Technology
- Storage + Gas engines
- Total capacity
- 750 MW
- Connected now
- 375 MW
- Still to connect
- 375 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000494
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 300 | 0 | 300 | None | Not stated | Built |
| 2 | 75 | 375 | 750 | 30 Jun 2026 | Gate 2 | Built |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 10 Oct 2026 registerStage 2: Status changed from Under Construction/Commissioning to Built
- 5 Oct 2026 registerStage 2: Given a Gate 2 connection offer
- 25 Aug 2026 registerStage 2: 75 MW now connected
- 28 Apr 2026 registerStage 1: Connection date removed (was 30 Jun 2025)
- 28 Apr 2026 registerStage 1: Status changed from Under Construction/Commissioning to Built
- 28 Apr 2026 registerStage 2: Connection date moved from 31 Oct 2025 to 30 Jun 2026 (+8 months)
- 20 Mar 2026 registerStage 1: 300 MW now connected
- 28 Nov 2025 registerRestructured from 1 stage (450 MW from 31 Oct 2029) to 1 stage (450 MW from 31 Oct 2025). First connection date −48 months
- 21 Nov 2025 registerRestructured from 1 stage (450 MW from 31 Oct 2025) to 1 stage (450 MW from 31 Oct 2029). First connection date +48 months
- 27 Jun 2025 registerStage 1: Connection date moved from 28 Nov 2024 to 30 Jun 2025 (+7 months)
- 28 Feb 2025 registerRestructured from 1 stage (750 MW from 28 Nov 2024) to 2 stages (300 MW from 28 Nov 2024, 450 MW from 31 Oct 2025)
- 26 Nov 2024 registerConnection date moved from 31 Oct 2024 to 28 Nov 2024 (+1 month)
- 27 Aug 2024 registerCustomer changed from THURROCK POWER LIMITED to THURROCK FLEXIBLE GENERATION LIMITED
- 28 Jul 2023 registerRestructured from 2 stages (300 MW from 31 Oct 2024, 450 MW from 31 Oct 2024) to 1 stage (750 MW from 31 Oct 2024)
- 30 Jun 2023 registerStage 1: Connection date moved from 31 Oct 2025 to 31 Oct 2024 (−12 months)
- 30 Jun 2023 registerStage 2: Connection date moved from 31 Oct 2026 to 31 Oct 2024 (−24 months)
- 30 May 2023 registerStage 1: Connection date moved from 1 Oct 2023 to 31 Oct 2025 (+25 months)
- 30 May 2023 registerStage 2: Connection date moved from 1 May 2024 to 31 Oct 2026 (+30 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Tilbury 275kV to Tilbury 275kV Substation)
- 30 Mar 2021 registerRenamed from Thurrock
- 26 Feb 2021 registerStage 1: Connection date moved from 10 Jan 2023 to 1 Oct 2023 (+9 months)
- 26 Feb 2021 registerStage 2: Connection date moved from 5 Jan 2024 to 1 May 2024 (+4 months)
Also at Tilbury 275kV Substation
Substation viewNo other projects in the register at this connection point.