THURROCK FLEXIBLE GENERATION LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Thurrock Power Station | Tilbury 275kV Substation | Thermal (gas, biomass, waste) | 375 | 30 Jun 2026 Past date +8 mo | Gate 2 | Built |
Recent changes
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Status changed from Under Construction/Commissioning to Built
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Given a Gate 2 connection offerGate 2
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 2: 75 MW now connectedConnected
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Connection date removed (was 30 Jun 2025)
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Status changed from Under Construction/Commissioning to Built
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 31 Oct 2025 to 30 Jun 2026 (+8 months)+8 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 1: 300 MW now connectedConnected
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Restructured from 1 stage (450 MW from 31 Oct 2029) to 1 stage (450 MW from 31 Oct 2025). First connection date −48 months−48 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Restructured from 1 stage (450 MW from 31 Oct 2025) to 1 stage (450 MW from 31 Oct 2029). First connection date +48 months+48 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Connection date moved from 28 Nov 2024 to 30 Jun 2025 (+7 months)+7 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Restructured from 1 stage (750 MW from 28 Nov 2024) to 2 stages (300 MW from 28 Nov 2024, 450 MW from 31 Oct 2025)
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Connection date moved from 31 Oct 2024 to 28 Nov 2024 (+1 month)+1 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Customer changed from THURROCK POWER LIMITED to THURROCK FLEXIBLE GENERATION LIMITED
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Restructured from 2 stages (300 MW from 31 Oct 2024, 450 MW from 31 Oct 2024) to 1 stage (750 MW from 31 Oct 2024)
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Connection date moved from 31 Oct 2025 to 31 Oct 2024 (−12 months)−12 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 31 Oct 2026 to 31 Oct 2024 (−24 months)−24 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Connection date moved from 1 Oct 2023 to 31 Oct 2025 (+25 months)+25 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 1 May 2024 to 31 Oct 2026 (+30 months)+30 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Substation name updated in the register (from Tilbury 275kV to Tilbury 275kV Substation)
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Renamed from Thurrock
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 1: Connection date moved from 10 Jan 2023 to 1 Oct 2023 (+9 months)+9 mo
- Thurrock Power StationEngland and Wales, Thermal (gas, biomass, waste)Stage 2: Connection date moved from 5 Jan 2024 to 1 May 2024 (+4 months)+4 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?