Enoch Hill 2 Wind Farm
RWE Renewables UK Onshore Wind Limited at Enoch Hill 2 Wind Farm 33kV Substation
- Connection date
- 30 Apr 2027
- Gate
- Gate 1
- Status
- Awaiting Consents
- Planning consent
- Granted 17 Jul 2025
East Ayrshire, reference 23/0469/PP · Source: REPD - Contract for Difference
- Allocation Round 7a
- Technology
- Storage + Onshore wind
- Total capacity
- 10 MW
- Connected now
- 0 MW
- Still to connect
- 10 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000478
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 25 Aug 2026 registerMarked as Gate 1
- 29 Aug 2025 registerConnection point changed from Enoch Hill 2 Wind Farm 132kV/33kV to Enoch Hill 2 Wind Farm 33kV Substation
- 29 Apr 2025 registerRenamed from Monquhill Wind Farm
- 29 Apr 2025 registerConnection point changed from Monquhill Wind Farm 132kV/33kV to Enoch Hill 2 Wind Farm 132kV/33kV
- 29 Apr 2025 registerTechnology changed from Onshore wind to Storage, Onshore wind
- 23 Dec 2022 registerConnection point changed from Monquhill Wind Farm 33kV to Monquhill Wind Farm 132kV/33kV
- 30 Jul 2021 registerCustomer changed from RWE RENEWABLES UK DEVELOPMENTS LIMITED to RWE RENEWABLES UK ONSHORE WIND LIMITED
- 26 Feb 2021 registerConnection date moved from 30 Apr 2025 to 30 Apr 2027 (+24 months)
Also at Enoch Hill 2 Wind Farm 33kV Substation
Substation viewNo other projects in the register at this connection point.