Mossy Hill Wind Farm
- Connection date
- 29 Jun 2029 +7 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted 27 May 2019
Shetland Islands, reference 2018/186/PPF · Source: REPD - Contract for Difference
- Allocation Round 4
- Technology
- Demand + Onshore wind
- Total capacity
- 40 MW
- Connected now
- 0 MW
- Still to connect
- 40 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000461
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 30 Oct 2026 registerCapacity changed from 48 MW to 40 MW
- 30 Oct 2026 registerConnection date moved from 30 Nov 2028 to 29 Jun 2029 (+7 months)
- 30 Oct 2026 registerGiven a Gate 2 connection offer
- 29 Oct 2024 registerConnection date moved from 1 Apr 2027 to 30 Nov 2028 (+20 months)
- 29 Oct 2024 registerTechnology changed from Onshore wind to Demand, Onshore wind
- 29 Aug 2023 registerCustomer changed from PEEL NRE WIND FARMS (NO. 1) LIMITED to MOSSY HILL SHETLAND LIMITED
- 31 Jan 2023 registerCapacity changed from 49.9 MW to 48 MW
- 31 Jan 2023 registerConnection date moved from 1 Apr 2026 to 1 Apr 2027 (+12 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Mossy Hill 132kV to Mossy Hill 132kV Substation)
- 30 Mar 2022 registerConnection date moved from 30 Apr 2025 to 1 Apr 2026 (+11 months)
- 30 Mar 2021 registerConnection date moved from 1 Apr 2024 to 30 Apr 2025 (+13 months)
- 26 Feb 2021 registerCustomer changed from Peel L&P Wind Farms (No. 1) Limited to Peel NRE Wind Farms (No. 1) Limited
- 26 Feb 2021 registerConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)
Also at Mossy Hill 132kV Substation
Substation viewNo other projects in the register at this connection point.