MOSSY HILL SHETLAND LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Mossy Hill Wind Farm | Mossy Hill 132kV Substation | Onshore wind | 40 | 29 Jun 2029 +7 mo | Gate 2 | Consents Approved |
Recent changes
- Mossy Hill Wind FarmNorth Scotland, Onshore windCapacity changed from 48 MW to 40 MW
- Mossy Hill Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Nov 2028 to 29 Jun 2029 (+7 months)+7 mo
- Mossy Hill Wind FarmNorth Scotland, Onshore windGiven a Gate 2 connection offerGate 2
- Mossy Hill Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2027 to 30 Nov 2028 (+20 months)+20 mo
- Mossy Hill Wind FarmNorth Scotland, Onshore windTechnology changed from Onshore wind to Demand, Onshore wind
- Mossy Hill Wind FarmNorth Scotland, Onshore windCustomer changed from PEEL NRE WIND FARMS (NO. 1) LIMITED to MOSSY HILL SHETLAND LIMITED
- Mossy Hill Wind FarmNorth Scotland, Onshore windCapacity changed from 49.9 MW to 48 MW
- Mossy Hill Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2026 to 1 Apr 2027 (+12 months)+12 mo
- Mossy Hill Wind FarmNorth Scotland, Onshore windSubstation name updated in the register (from Mossy Hill 132kV to Mossy Hill 132kV Substation)
- Mossy Hill Wind FarmNorth Scotland, Onshore windConnection date moved from 30 Apr 2025 to 1 Apr 2026 (+11 months)+11 mo
- Mossy Hill Wind FarmNorth Scotland, Onshore windConnection date moved from 1 Apr 2024 to 30 Apr 2025 (+13 months)+13 mo
- Mossy Hill Wind FarmNorth Scotland, Onshore windCustomer changed from Peel L&P Wind Farms (No. 1) Limited to Peel NRE Wind Farms (No. 1) Limited
- Mossy Hill Wind FarmNorth Scotland, Onshore windConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?