Iron Acton
- Connection date
- 13 Apr 2026
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 120 MW
- Connected now
- 0 MW
- Still to connect
- 120 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000455
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 49.9 | 49.9 | 13 Apr 2026 | Not stated | Consents Approved |
| 2 | 0 | 70.1 | 120 | 31 Oct 2028 | Not stated | Consents Approved |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 31 Oct 2025 registerStage 1: Connection date moved from 30 Jun 2025 to 13 Apr 2026 (+9 months)
- 28 Jul 2023 registerConnection point changed from Iron Acton 132kV Substation to Iron Acton 275kV Substation
- 30 May 2023 registerStage 1: Connection date moved from 31 Oct 2023 to 30 Jun 2025 (+20 months)
- 28 Feb 2023 registerRenamed from Iron Acton Tertiary Connection
- 28 Feb 2023 registerConnection point changed from Iron Acton GSP to Iron Acton 132kV Substation
- 28 Feb 2023 registerStage 1: Status changed from Scoping to Consents Approved
- 28 Feb 2023 registerStage 1: Technology changed from Gas engines to Storage
- 28 Feb 2023 registerStage 2: Capacity changed from 120 MW to 70.1 MW
- 28 Feb 2023 registerStage 2: Status changed from Scoping to Consents Approved
- 28 Feb 2023 registerStage 2: Technology changed from Gas engines to Storage
- 23 Dec 2022 registerSubstation name updated in the register (from Iron Acton to Iron Acton GSP)
- 28 Sep 2021 registerRestructured from 1 stage (49.9 MW from 1 Oct 2022) to 2 stages (49.9 MW from 31 Oct 2023, 120 MW from 31 Oct 2028). First connection date +13 months
- 26 Feb 2021 registerConnection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)
Also at Iron Acton 275kV Substation
Substation viewNo other projects in the register at this connection point.