HD000ACT LTD
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Iron Acton | Iron Acton 275kV Substation | Storage | 120 | 13 Apr 2026 Past date | Not stated | Consents Approved |
Recent changes
- Iron ActonEngland and Wales, StorageStage 1: Connection date moved from 30 Jun 2025 to 13 Apr 2026 (+9 months)+9 mo
- Iron ActonEngland and Wales, StorageConnection point changed from Iron Acton 132kV Substation to Iron Acton 275kV Substation
- Iron ActonEngland and Wales, StorageStage 1: Connection date moved from 31 Oct 2023 to 30 Jun 2025 (+20 months)+20 mo
- Iron ActonEngland and Wales, StorageRenamed from Iron Acton Tertiary Connection
- Iron ActonEngland and Wales, StorageConnection point changed from Iron Acton GSP to Iron Acton 132kV Substation
- Iron ActonEngland and Wales, StorageStage 1: Status changed from Scoping to Consents Approved
- Iron ActonEngland and Wales, StorageStage 1: Technology changed from Gas engines to Storage
- Iron ActonEngland and Wales, StorageStage 2: Capacity changed from 120 MW to 70.1 MW
- Iron ActonEngland and Wales, StorageStage 2: Status changed from Scoping to Consents Approved
- Iron ActonEngland and Wales, StorageStage 2: Technology changed from Gas engines to Storage
- Iron ActonEngland and Wales, StorageSubstation name updated in the register (from Iron Acton to Iron Acton GSP)
- Iron ActonEngland and Wales, StorageRestructured from 1 stage (49.9 MW from 1 Oct 2022) to 2 stages (49.9 MW from 31 Oct 2023, 120 MW from 31 Oct 2028). First connection date +13 months+13 mo
- Iron ActonEngland and Wales, StorageConnection date moved from 10 Jan 2022 to 1 Oct 2022 (+9 months)+9 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose