Blarghour Wind
- Connection date
- 1 Apr 2029
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 67.2 MW
- Connected now
- 0 MW
- Still to connect
- 67.2 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000398
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerCapacity changed from 73.1 MW to 67.2 MW
- 27 Jun 2025 registerConnection date moved from 31 Oct 2027 to 1 Apr 2029 (+17 months)
- 28 Jul 2023 registerConnection date moved from 30 Apr 2026 to 31 Oct 2027 (+18 months)
- 23 Dec 2022 registerSubstation name updated in the register (from Blarghour to Blarghour Substation)
- 30 Mar 2022 registerConnection date moved from 30 Oct 2025 to 30 Apr 2026 (+6 months)
- 28 Jan 2022 registerStatus changed from Scoping to Consents Approved
Also at Blarghour Substation
Substation viewNo other projects in the register at this connection point.