BLARGHOUR WIND FARM LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Blarghour Wind | Blarghour Substation | Onshore wind | 67.2 | 1 Apr 2029 | Not stated | Consents Approved |
Recent changes
- Blarghour WindNorth Scotland, Onshore windCapacity changed from 73.1 MW to 67.2 MW
- Blarghour WindNorth Scotland, Onshore windConnection date moved from 31 Oct 2027 to 1 Apr 2029 (+17 months)+17 mo
- Blarghour WindNorth Scotland, Onshore windConnection date moved from 30 Apr 2026 to 31 Oct 2027 (+18 months)+18 mo
- Blarghour WindNorth Scotland, Onshore windSubstation name updated in the register (from Blarghour to Blarghour Substation)
- Blarghour WindNorth Scotland, Onshore windConnection date moved from 30 Oct 2025 to 30 Apr 2026 (+6 months)+6 mo
- Blarghour WindNorth Scotland, Onshore windStatus changed from Scoping to Consents Approved
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?