Windy Standard III Wind Farm
- Connection date
- 1 Jun 2026
- Gate
- Gate 2
- Status
- Consents Approved
- Technology
- Onshore wind
- Total capacity
- 87.6 MW
- Connected now
- 0 MW
- Still to connect
- 87.6 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000359
- In the register since
- January 2021 or earlier
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 43.5 | 43.5 | 1 Jun 2026 | Gate 2 | Consents Approved |
| 2 | 0 | 44.1 | 87.6 | 31 Oct 2027 | Gate 2 | Consents Approved |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStage 1: Status changed from Awaiting Consents to Consents Approved
- 18 Sep 2026 registerStage 2: Status changed from Awaiting Consents to Consents Approved
- 23 Jun 2026 registerStage 1: Given a Gate 2 connection offer
- 23 Jun 2026 registerStage removed (10.5 MW from 1 Jun 2026)
- 19 Jun 2026 registerStage 2: Capacity changed from 42 MW to 44.1 MW
- 19 Jun 2026 registerStage 2: Connection date moved from 1 Jun 2026 to 31 Oct 2027 (+17 months)
- 19 Jun 2026 registerStage 2: Given a Gate 2 connection offer
- 29 Oct 2024 registerStage 1: Connection date moved from 30 Jun 2024 to 1 Jun 2026 (+23 months)
- 29 Oct 2024 registerStage 2: Connection date moved from 30 Jun 2024 to 1 Jun 2026 (+23 months)
- 29 Oct 2024 registerStage 3: Connection date moved from 30 Jun 2029 to 1 Jun 2026 (−37 months)
- 27 Sep 2024 registerCustomer changed from Brockloch Rig III Ltd to Windy Standard III Ltd
- 27 Sep 2024 registerSubstation name updated in the register (from Dun Hill 132/33kV Substation to Dun Hill 132/33kV)
- 30 Jun 2023 registerCustomer changed from WINDY STANDARD III LIMITED to Brockloch Rig III Ltd
- 29 Nov 2022 registerCustomer changed from BROCKLOCH RIG III LIMITED to WINDY STANDARD III LIMITED
- 30 Mar 2022 registerNew stage added (42 MW from 30 Jun 2024)
- 30 Mar 2022 registerNew stage added (10.5 MW from 30 Jun 2029)
- 30 Mar 2021 registerConnection date moved from 28 Apr 2023 to 30 Jun 2024 (+14 months)
Also at Dun Hill 132/33kV
Substation view2 other projects, 110 MW still to connect at this substation in total.