Windy Standard II (Brockloch Rig) Wind Farm
- Connection date
- Connected
- Gate
- Not stated
- Status
- Built
- Technology
- Onshore wind
- Total capacity
- 61.5 MW
- Connected now
- 61.5 MW
- Still to connect
- 0 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000233
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerStage removed (13.5 MW from 30 Jun 2024)
- 27 Sep 2024 registerSubstation name updated in the register (from Dun Hill 132/33kV Substation to Dun Hill 132/33kV)
- 31 May 2022 registerStage 2: Connection date moved from 30 Apr 2022 to 30 Jun 2024 (+26 months)
Also at Dun Hill 132/33kV
Substation view2 other projects, 110 MW still to connect at this substation in total.