Inch Cape Offshore Wind Farm Platform 2
- Connection date
- 21 Feb 2026
- Gate
- Gate 2
- Status
- Under Construction/Commissioning
- Technology
- Offshore wind
- Total capacity
- 540 MW
- Connected now
- 0 MW
- Still to connect
- 540 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Direct Connection
- Region
- South Scotland
- Project number
- PRO-000349
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Consents Approved to Under Construction/Commissioning
- 14 Aug 2026 registerConnection point changed from Cockenzie 400/275kV to Cockenzie 275kV substation
- 14 Aug 2026 registerGiven a Gate 2 connection offer
- 28 Feb 2025 registerConnection date moved from 21 Jun 2026 to 21 Feb 2026 (−4 months)
- 29 Oct 2024 registerConnection point changed from Inch Cape Platform 2 220/66kV Offshore Substation to Cockenzie 400/275kV
- 29 Oct 2024 registerConnection date moved from 1 Apr 2025 to 21 Jun 2026 (+15 months)
- 29 Apr 2022 registerConnection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)
- 26 Feb 2021 registerConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)
Also at Cockenzie 275kV substation
Substation viewNo other projects in the register at this connection point.