INCH CAPE OFFSHORE LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| Inch Cape Offshore Wind Farm Platform 1 | Cockenzie 400/275kV | Offshore wind | 540 | 21 Feb 2026 Past date | Gate 2 | Under Construction/Commissioning |
| Inch Cape Offshore Wind Farm Platform 2 | Cockenzie 275kV substation | Offshore wind | 540 | 21 Feb 2026 Past date | Gate 2 | Under Construction/Commissioning |
Recent changes
- Inch Cape Offshore Wind Farm Platform 1South Scotland, Offshore windStatus changed from Consents Approved to Under Construction/Commissioning
- Inch Cape Offshore Wind Farm Platform 2South Scotland, Offshore windStatus changed from Consents Approved to Under Construction/Commissioning
- Inch Cape Offshore Wind Farm Platform 1South Scotland, Offshore windGiven a Gate 2 connection offerGate 2
- Inch Cape Offshore Wind Farm Platform 2South Scotland, Offshore windConnection point changed from Cockenzie 400/275kV to Cockenzie 275kV substation
- Inch Cape Offshore Wind Farm Platform 2South Scotland, Offshore windGiven a Gate 2 connection offerGate 2
- Inch Cape Offshore Wind Farm Platform 1South Scotland, Offshore windConnection date moved from 21 Jun 2026 to 21 Feb 2026 (−4 months)−4 mo
- Inch Cape Offshore Wind Farm Platform 2South Scotland, Offshore windConnection date moved from 21 Jun 2026 to 21 Feb 2026 (−4 months)−4 mo
- Inch Cape Offshore Wind Farm Platform 1South Scotland, Offshore windConnection point changed from Cockenzie 400/275/33kV to Cockenzie 400/275kV
- Inch Cape Offshore Wind Farm Platform 1South Scotland, Offshore windConnection date moved from 1 Apr 2025 to 21 Jun 2026 (+15 months)+15 mo
- Inch Cape Offshore Wind Farm Platform 2South Scotland, Offshore windConnection point changed from Inch Cape Platform 2 220/66kV Offshore Substation to Cockenzie 400/275kV
- Inch Cape Offshore Wind Farm Platform 2South Scotland, Offshore windConnection date moved from 1 Apr 2025 to 21 Jun 2026 (+15 months)+15 mo
- Inch Cape Offshore Wind Farm Platform 1South Scotland, Offshore windConnection point changed from Cockenzie 275kV Substation to Cockenzie 400/275/33kV
- Inch Cape Offshore Wind Farm Platform 1South Scotland, Offshore windConnection point changed from Inch Cape Platform 1 220/66kV Offshore Substation to Cockenzie 275kV Substation
- Inch Cape Offshore Wind Farm Platform 1South Scotland, Offshore windConnection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)+12 mo
- Inch Cape Offshore Wind Farm Platform 2South Scotland, Offshore windConnection date moved from 1 Apr 2024 to 1 Apr 2025 (+12 months)+12 mo
- Inch Cape Offshore Wind Farm Platform 1South Scotland, Offshore windConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)+3 mo
- Inch Cape Offshore Wind Farm Platform 2South Scotland, Offshore windConnection date moved from 4 Jan 2024 to 1 Apr 2024 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?