Sneddon Law Wind
SNEDDON LAW COMMUNITY WIND COMPANY LTD at Kilmarnock Town 275/33kV Substation
- Connection date
- Left 26 Mar 2024
- Gate
- Not stated
- Status
- Under Construction/Commissioning
- Technology
- Onshore wind
- Total capacity
- 30 MW
- Connected now
- 0 MW
- Still to connect
- 30 MW
- Transmission owner
- SP Energy Networks (SPT)
- Agreement type
- Embedded
- Region
- South Scotland
- Project number
- PRO-000324
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 146 registers from 29 Jan 2021 to 20 Oct 2026.
- 26 Mar 2024 registerLeft the register (30 MW from 31 Mar 2023)
- 23 Dec 2022 registerSubstation name updated in the register (from Kilmarnock Town 275/33kV to Kilmarnock Town 275/33kV Substation)
- 29 Nov 2022 registerConnection date moved from 31 Oct 2018 to 31 Mar 2023 (+53 months)
Also at Kilmarnock Town 275/33kV Substation
Substation view1 other project, 60 MW still to connect at this substation in total.