EAST ANGLIA THREE LIMITED
Customer named in the TEC register
Projects
| Project | Connection site | Technology | Queued MW | Connection date | Gate | Status |
|---|---|---|---|---|---|---|
| East Anglia Three | East Anglia Project Three Offshore Platform | Offshore wind | 1,320 | 31 Jan 2026 Past date | Not stated | Consents Approved |
Recent changes
- East Anglia ThreeEngland and Wales, Offshore windRestructured from 2 stages (1,200 MW from 31 Jan 2026, 120 MW from 31 Dec 2028) to 1 stage (1,320 MW from 31 Jan 2026)
- East Anglia ThreeEngland and Wales, Offshore windStage 2: Capacity changed from 100 MW to 120 MW
- East Anglia ThreeEngland and Wales, Offshore windConnection point changed from EA3A and EA3B 320/66kV Offshore Platform to East Anglia Project Three Offshore Platform
- East Anglia ThreeEngland and Wales, Offshore windStage 1: Capacity changed from 600 MW to 1,200 MW
- East Anglia ThreeEngland and Wales, Offshore windStage 1: Connection date moved from 1 Apr 2023 to 31 Jan 2026 (+34 months)+34 mo
- East Anglia ThreeEngland and Wales, Offshore windStage 2: Capacity changed from 600 MW to 100 MW
- East Anglia ThreeEngland and Wales, Offshore windStage 2: Connection date moved from 1 Apr 2023 to 31 Dec 2028 (+69 months)+69 mo
- East Anglia ThreeEngland and Wales, Offshore windRenamed from East Anglia 3
- East Anglia ThreeEngland and Wales, Offshore windStage 1: Connection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)+3 mo
- East Anglia ThreeEngland and Wales, Offshore windStage 2: Connection date moved from 4 Jan 2023 to 1 Apr 2023 (+3 months)+3 mo
Price what a delay would do to your project
QueueWatch reports what changed in the public TEC register. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?