Strathy South Wind
- Connection date
- 30 Sep 2030 +41 months since 9 Dec
- Gate
- Gate 2
- Status
- Consents Approved
- Planning consent
- Granted on appeal 27 Apr 2018
Scottish Government (S36), reference EC00003113 · Source: REPD - Contract for Difference
- Allocation Round 5
- Technology
- Onshore wind
- Total capacity
- 208 MW
- Connected now
- 0 MW
- Still to connect
- 208 MW
- Transmission owner
- SSEN Transmission (SHET)
- Agreement type
- Direct Connection
- Region
- North Scotland
- Project number
- PRO-000183
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 18 Sep 2026 registerStatus changed from Scoping to Consents Approved
- 28 Aug 2026 registerConnection date moved from 28 May 2027 to 30 Sep 2030 (+40 months)
- 28 Aug 2026 registerGiven a Gate 2 connection offer
- 25 Aug 2026 registerConnection date moved from 25 Apr 2027 to 28 May 2027 (+1 month)
- 30 Jul 2024 registerConnection date moved from 1 Dec 2025 to 25 Apr 2027 (+17 months)
- 28 Sep 2021 registerRestructured from 3 stages (133 MW from 1 Dec 2025, 25 MW from 1 Dec 2025, 50 MW from 1 Dec 2025) to 1 stage (208 MW from 1 Dec 2025)
- 26 Feb 2021 registerStage 1: Connection date moved from 12 Jan 2025 to 1 Dec 2025 (+11 months)
- 26 Feb 2021 registerStage 2: Connection date moved from 12 Jan 2025 to 1 Dec 2025 (+11 months)
- 26 Feb 2021 registerStage 3: Connection date moved from 12 Jan 2025 to 1 Dec 2025 (+11 months)
Also at Strathy South 132/33kV Substation
Substation viewNo other projects in the register at this connection point.