- Connection date
- Increase at an existing station: +50 MW from 30 Oct 2029
- Gate
- Not stated
- Status
- Built
- Technology
- Gas (CCGT)
- Total capacity
- 850 MW
- Connected now
- 800 MW
- Still to connect
- 50 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000103
- In the register since
- January 2021 or earlier
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 29 Jul 2025 registerCapacity changed from 0 MW to 50 MW
- 29 Jul 2025 registerConnection date set to 30 Oct 2029
- 23 Dec 2022 registerSubstation name updated in the register (from Coryton South 400kV to Coryton South 400kV Substation)
Also at Coryton South 400kV Substation
Substation view1 other project, 1.1 GW still to connect at this substation in total. 450 MW is due to connect here before this project’s connection date of 30 Oct 2029.