Gateway Energy Centre Power Station
GATEWAY ENERGY CENTRE LIMITED at Coryton South 400kV Substation
- Connection date
- 30 Jun 2029
- Gate
- Not stated
- Status
- Consents Approved
- Technology
- Storage
- Total capacity
- 1,000 MW
- Connected now
- 0 MW
- Still to connect
- 1,000 MW
- Transmission owner
- National Grid Electricity Transmission (NGET)
- Agreement type
- Direct Connection
- Region
- England and Wales
- Project number
- PRO-000045
- In the register since
- January 2021 or earlier
What would CMP470’s commitment fee do to a battery like this? See the use case: Will CMP470’s commitment fee clear the battery queue?
Stages
| Stage | Connected MW | Adds MW | Cumulative MW | Date | Gate | Status |
|---|---|---|---|---|---|---|
| 1 | 0 | 450 | 450 | 30 Jun 2029 | Not stated | Consents Approved |
| 2 | 0 | 550 | 1,000 | 30 Oct 2029 | Not stated | Consents Approved |
Change history
Every change to this project across 151 registers from 29 Jan 2021 to 5 Nov 2026.
- 27 Jun 2025 registerStage 1: Connection date moved from 30 Sep 2025 to 30 Jun 2029 (+45 months)
- 31 Oct 2023 registerStage 1: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Storage
- 31 Oct 2023 registerStage 2: Technology changed from Gas (CCGT), Storage, Gas (OCGT) to Storage
- 23 Dec 2022 registerSubstation name updated in the register (from Coryton South 400kV to Coryton South 400kV Substation)
- 29 Nov 2022 registerStage 1: Capacity changed from 620 MW to 450 MW
- 29 Nov 2022 registerStage 1: Connection date moved from 30 Sep 2024 to 30 Sep 2025 (+12 months)
- 29 Nov 2022 registerStage 2: Capacity changed from 380 MW to 550 MW
- 29 Nov 2022 registerStage 2: Connection date moved from 30 Sep 2025 to 30 Oct 2029 (+49 months)
- 30 Apr 2021 registerStage 1: Connection date moved from 30 Sep 2023 to 30 Sep 2024 (+12 months)
- 30 Apr 2021 registerStage 2: Connection date moved from 30 Sep 2024 to 30 Sep 2025 (+12 months)
Also at Coryton South 400kV Substation
Substation view1 other project, 1.1 GW still to connect at this substation in total.