St Rollox 9.5MW BESS
Springburn Depot SPV Limited at Charlotte Street
SPEN Embedded Capacity Register >1MW, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Oct 2027
- Status
- Accepted to connect
- Customer
- Springburn Depot SPV Limited
- Site name
- St Rollox 9.5MW BESS
- Address
- Charles St, Glasgow, Glasgow City, G21 2PX
- Grid reference
- Easting 260591, northing 666519
- Licence area
- Central and Southern Scotland (SPD)
- Grid supply point
- Charlotte Street
- Bulk supply point
- Not stated
- Primary substation
- ROTTEN ROW B (11kV)
- Connection voltage
- 11 kV
- Technology group
- Storage
- Energy source 1
- Stored Energy, Storage - Electrochemical (Batteries): 10.35 MW registered
- Energy source 2
- Solar, Photovoltaic: 10 MW registered
- Registered capacity
- 20.35 MW
- Change to maximum export capacity
- 9.5 MW
- Change to maximum import capacity
- 9.5 MW
- Flexible connection
- Yes
- In a connection queue
- Yes
- Date accepted
- 5 Jun 2024
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SPEN
- Transmission reinforcement reference
- Not stated
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 25 Jun 2025
- Tracked since
- March 2026 edition
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Change history
Tracked since the March 2026 edition, across 7 editions.
Changes to the details QueueWatch tracks, newest first.
No change to any detail QueueWatch tracks.
Also at Charlotte Street
GSP view3 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 27.3 MW: 7 MW connected, 20.3 MW accepted to connect.
- University of Strathclyde CHPUniversity of Strathclyde, Gas and other fossil, ROTTEN ROW (11kV) primaryConnected3.3 MW
- Royal Infirmary CHPNHS Greater Glasgow & Clyde, Gas and other fossil, HUNTER STREET (11kV) primaryConnected2 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?