QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Netherton Gas

At Wishaw

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Date connected
Not stated
Status
Connected
Customer
Not stated
Site name
Netherton Gas
Address
Site West of 22A22F Netherdale Road, Netherton Industrial Estate, Wishaw, North Lanarkshire, ML2 0ER
Grid reference
Easting 278333, northing 654697
Licence area
Central and Southern Scotland (SPD)
Grid supply point
Wishaw
Bulk supply point
Not stated
Primary substation
Larkhall (11KV)
Connection voltage
33 kV
Technology group
Gas and other fossil
Energy source 1
Fossil - Gas, Gas turbine (OCGT): 19.9 MW registered
Registered capacity
19.9 MW
Maximum export capacity
19.9 MW
Maximum import capacity
0 MW
Flexible connection
No
In a connection queue
No
Date accepted
17 Apr 2018
Target energisation date
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
14 Sep 2020
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to the details QueueWatch tracks, newest first.

No change to any detail QueueWatch tracks.

Also at Wishaw

GSP view

10 other sites at this grid supply point in the September 2026 edition, 5 of them at Larkhall (11KV), the same primary substation. In all, the sites here total 49.6 MW: 47.4 MW connected, 2.2 MW accepted to connect.

See all 10

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?