Langlands Gate BESS
Advance Grid Solutions Limited at East Kilbride South
SPEN Embedded Capacity Register >1MW, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 31 Aug 2027
- Status
- Accepted to connect
- Customer
- Advance Grid Solutions Limited
- Site name
- Langlands Gate BESS
- Address
- Langlands Business & Technology Park, Whitehills, East Kilbride, G75 0ZY
- Grid reference
- Easting 265901, northing 651246
- Licence area
- Central and Southern Scotland (SPD)
- Grid supply point
- East Kilbride South
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 33 kV
- Technology group
- Storage
- Energy source 1
- Stored Energy, Storage - Electrochemical (Batteries): 17 MW registered
- Registered capacity
- 17 MW
- Change to maximum export capacity
- 16.5 MW
- Change to maximum import capacity
- 16.5 MW
- Flexible connection
- No
- In a connection queue
- Yes
- Date accepted
- 16 Aug 2023
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SPEN
- Transmission reinforcement reference
- SPT-RI-1968, SPT-RI-2520, SPT-RI-3262, SPT-RI-4119
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 30 Aug 2023
- Tracked since
- March 2026 edition
Change history
Tracked since the March 2026 edition, across 7 editions.
Changes to its status, capacity, technology or customer, newest first.
No change to its status, capacity, technology or customer.
Also at East Kilbride South
GSP view13 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 305 MW: 133 MW connected, 172 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose