QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

Kennishead BESS

Starlight Energy UK Ltd at Haggs Road

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2031
Status
Accepted to connect
Customer
Starlight Energy UK Ltd
Site name
Kennishead BESS
Address
Land at Kennishead Farm, Kennishead, Glasgow, East Renfrewshire, G46 8SF
Grid reference
Easting 254101, northing 660323
Licence area
Central and Southern Scotland (SPD)
Grid supply point
Haggs Road
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Storage
Energy source 1
Stored Energy, Storage - Electrochemical (Batteries): 40 MW registered
Registered capacity
40 MW
Change to maximum export capacity
40 MW
Change to maximum import capacity
40 MW
Flexible connection
Yes
In a connection queue
Yes
Date accepted
23 Jun 2023
Date connected
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
29 Nov 2024
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at Haggs Road

GSP view

No other site in SPEN's September 2026 edition is at this grid supply point.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose