Glasgow BESS (South Street BESS)
Circle Power Ltd at Partick
SPEN Embedded Capacity Register >1MW, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 30 Jun 2031
- Status
- Accepted to connect
- Customer
- Circle Power Ltd
- Site name
- Glasgow BESS (South Street BESS)
- Address
- 239 South Street, Glasgow, Glasgow City, G14 0BX
- Grid reference
- Easting 253324, northing 666892
- Licence area
- Central and Southern Scotland (SPD)
- Grid supply point
- Partick
- Bulk supply point
- Not stated
- Primary substation
- Not stated
- Connection voltage
- 33 kV
- Technology group
- Storage
- Energy source 1
- Stored Energy, Storage - Electrochemical (Batteries): 64 MW registered
- Registered capacity
- 64 MW
- Change to maximum export capacity
- 63 MW
- Change to maximum import capacity
- 63 MW
- Flexible connection
- Yes
- In a connection queue
- Yes
- Date accepted
- 12 Oct 2023
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SPEN
- Transmission reinforcement reference
- Not stated
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 27 Jun 2024
- Tracked since
- March 2026 edition
What would CMP470’s commitment fee do to a battery like this? Read our study: Will CMP470’s commitment fee clear the battery queue?
Change history
Tracked since the March 2026 edition, across 7 editions.
Changes to the details QueueWatch tracks, newest first.
No change to any detail QueueWatch tracks.
Also at Partick
GSP viewNo other site in SPEN’s September 2026 edition is at this grid supply point.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?