Drumgray Energy from Waste

FCC Environment at Cumbernauld

SPEN Embedded Capacity Register >1MW, September 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
27 Oct 2028
Status
Accepted to connect
Customer
FCC Environment
Site name
Drumgray Energy from Waste
Address
Off Darngavil Road, Airdrie, North Lanarkshire, ML6 7TD
Grid reference
Easting 278565, northing 668730
Licence area
Central and Southern Scotland (SPD)
Grid supply point
Cumbernauld
Bulk supply point
Not stated
Primary substation
Not stated
Connection voltage
33 kV
Technology group
Bioenergy and waste
Energy source 1
Biofuel - Landfill gas, Steam-gas turbine (CCGT): 32.082 MW registered
Registered capacity
32.082 MW
Change to maximum export capacity
29.9 MW
Change to maximum import capacity
20 MW
Flexible connection
No
In a connection queue
Yes
Date accepted
26 Apr 2021
Date connected
Not stated
Distribution reinforcement reference
Not published by SPEN
Transmission reinforcement reference
Not stated
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
19 Feb 2025
Tracked since
March 2026 edition

Change history

Tracked since the March 2026 edition, across 7 editions.

Changes to its status, capacity, technology or customer, newest first.

No change to its status, capacity, technology or customer.

Also at Cumbernauld

GSP view

13 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 171 MW: 71 MW connected, 100 MW accepted to connect.

See all 13

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose