Aston Grange PV
At Frodsham
SPEN Embedded Capacity Register >1MW, September 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 19 Jan 2023
- Status
- Accepted to connect
- Planning consent
- Application submitted 24 Feb 2025
Cheshire West and Chester, reference 25/00100/FULEIA · Source: REPD - Customer
- Not stated
- Site name
- Aston Grange PV
- Address
- Wirral
- Grid reference
- Not stated
- Licence area
- Merseyside, Cheshire and North Wales (SPM)
- Grid supply point
- Frodsham
- Bulk supply point
- DUTTON GT2 / MOORE GT1 / PERCIVAL LA GT1
- Primary substation
- Not stated
- Connection voltage
- 33 kV
- Technology group
- Solar
- Energy source 1
- Solar, Photovoltaic: 22.99 MW registered
- Registered capacity
- 22.99 MW
- Change to maximum export capacity
- 20 MW
- Change to maximum import capacity
- 6 MW
- Flexible connection
- Not stated
- In a connection queue
- Yes
- Date accepted
- Not stated
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SPEN
- Transmission reinforcement reference
- Not stated
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 29 Jan 2026
- Tracked since
- March 2026 edition
Change history
Tracked since the March 2026 edition, across 7 editions.
Changes to the details QueueWatch tracks, newest first.
No change to any detail QueueWatch tracks.
Also at Frodsham
GSP view15 other sites at this grid supply point in the September 2026 edition. In all, the sites here total 376 MW: 233 MW connected, 143 MW accepted to connect.
- Runcorn Flexible GasGEN Runcorn Flexible Gas Generating Plan, Gas and other fossil, ASTMOOR IND EST T1 / MACKAMAX T1 / MERSEY RD T1 / PICOW FARM RD T1 primaryConnected5.13 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
Planning consent
The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.