Kaimes
Grid supply point in Central and Southern Scotland (SPD)
SPEN Embedded Capacity Register >1MW, September 2026 edition
Capacity by technology
| Technology | Sites | Capacity | Connected | Accepted to connect |
|---|---|---|---|---|
| Wind | 4 | 98.4 MW | 30 MW | 68.4 MW |
| Storage | 1 | 52.8 MW | – | 52.8 MW |
| Solar | 1 | 5 MW | – | 5 MW |
| Gas and other fossil | 1 | 2.5 MW | 2.5 MW | – |
| Bioenergy and waste | 1 | 1.2 MW | 1.2 MW | – |
Storage capacity in MWh: not published by SPEN.
Each site is grouped by its first energy source, as the register names it.
How busy is each primary substation?
Each primary substation at this grid supply point in the September 2026 edition, under the bulk supply point its register gives. Select a row to see its sites.
Site, company and substation names are shown as they appear in the registers, including capitalisation.
| Primary substation | Bulk supply point | Sites | Connected | Accepted to connect | |||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| Not stated | 1 | 2.5 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 2.5 MW: 2.5 MW connected
| |||||||||||||||||||||||||||||||||||||||
| Not stated | 1 | 1.2 MW | – | ||||||||||||||||||||||||||||||||||||
1 site, 1.2 MW: 1.2 MW connected
| |||||||||||||||||||||||||||||||||||||||
| Not stated | 6 | 30 MW | 126 MW | ||||||||||||||||||||||||||||||||||||
6 sites, 156 MW: 30 MW connected, 126 MW accepted to connect
| |||||||||||||||||||||||||||||||||||||||
What changed recently
Changes to sites here found in both editions of each pair, newest first.
August 2026 edition to September 2026 edition: 8 sites matched. Every August site and every September site at this grid supply point had a match in the other edition.
- Wull Muir Wind FarmAugust 2026 editionFlexible connection changed from “no” to “yes”
- Wull Muir Wind FarmAugust 2026 editionIn a connection queue changed from “no” to “yes”
- Wull Muir Wind FarmJuly 2026 editionTarget energisation date not stated (1 Oct 2029 in the June 2026 edition)
- Bowbeat Wind Energy HubMay 2026 editionCustomer stated as Belltown Power UK Limited (not stated in the April 2026 edition)
- Wull Muir Wind FarmMay 2026 editionFlexible connection changed from “yes” to “no”
- Wull Muir Wind FarmMay 2026 editionIn a connection queue changed from “yes” to “no”
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?
How power reaches a site
A grid supply point (GSP) is where the national grid hands power to the local network. A bulk supply point (BSP) steps it down to a lower voltage for an area. A primary substation steps it down again for the streets and sites nearby. Most small and medium sites connect at a primary. Not every network has all three levels.