SCOTSTON FARM
At COUPAR ANGUS
SSEN Embedded Capacity Register, November 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 2 Sep 2027
- Status
- Accepted to connect
- Customer
- Not stated
- Site name
- SCOTSTON FARM
- Address
- SCOTSTON FARM, DUNDEE, ANGUS, DD3 0QT
- Grid reference
- Easting 333537, northing 738971
- Licence area
- North of Scotland (SHEPD)
- Grid supply point
- COUPAR ANGUS
- Bulk supply point
- Not stated
- Primary substation
- LEOCH
- Connection voltage
- 33 kV
- Technology group
- Wind
- Energy source 1
- WIND, ONSHORE WIND TURBINES: 2 MW registered
- Registered capacity
- 2 MW
- Change to maximum export capacity
- 2 MW
- Change to maximum import capacity
- 0.015 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 2 Sep 2026
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 14 Sep 2026
- Tracked since
- September 2026 edition
Change history
Tracked since the September 2026 edition, across 3 editions.
Changes to the details QueueWatch tracks, newest first.
No change to any detail QueueWatch tracks.
Also at COUPAR ANGUS
GSP view17 other sites at this grid supply point in the November 2026 edition. In all, the sites here total 717 MW: 101 MW connected, 616 MW accepted to connect.
- KEITHICK ESTATE SOLAR, AND BATTERY STORAGE PLANTECODEV GROUP LTD, Solar, COUPAR ANGUS GRID primaryAccepted112.5 MW
- GREEN BURN WIND FARMGREEN CAT RENEWABLES, Other or not stated, COUPAR ANGUS GRID primaryAccepted49.8 MW
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose
See how we’d price it: Sell now, or wait for your Gate 2 offer?