NEWTON OF PARK BESS 2
OPDE UK LTD at NAIRN
SSEN Embedded Capacity Register, March 2026 edition
Site, company and substation names are shown as they appear in the registers, including capitalisation.
- Target energisation date
- 3 Nov 2026
- Status
- Accepted to connect
- Customer
- OPDE UK LTD
- Site name
- NEWTON OF PARK BESS 2
- Address
- NAIRN, HIGHLAND, IV12 5RL
- Grid reference
- Easting 291324, northing 854809
- Licence area
- North of Scotland (SHEPD)
- Grid supply point
- NAIRN
- Bulk supply point
- Not stated
- Primary substation
- NAIRN GRID
- Connection voltage
- Not stated
- Technology group
- Storage
- Energy source 1
- STORED ENERGY (ALL STORED ENERGY IRRESPECTVE OF THE ORIGINAL ENERGY SOURCE), STORAGE - ELECTROCHEMICAL (BATTERIES): 52.68 MW registered
- Registered capacity
- 52.68 MW
- Change to maximum export capacity
- 52.621 MW
- Change to maximum import capacity
- 52.621 MW
- Flexible connection
- Not stated
- In a connection queue
- Not published by SSEN
- Date accepted
- 3 Nov 2025
- Date connected
- Not stated
- Distribution reinforcement reference
- Not published by SSEN
- Transmission reinforcement reference
- Not published by SSEN
- Export MPAN
- Not stated
- Import MPAN
- Not stated
- Last updated
- 12 Mar 2026
- Tracked since
- December 2025 edition
Change history
Tracked from the December 2025 edition to the March 2026 edition, across 3 editions. Not found in the February 2026 edition.
Changes to its status, capacity, technology or customer, newest first.
- April 2026 editionNot found in this edition by its MPAN, grid reference or name and postcode
- February 2026 editionNot found in this edition by its MPAN, grid reference or name and postcode
No change to its status, capacity, technology or customer.
Also at NAIRN
GSP view4 other sites at this grid supply point in the September 2026 edition, 1 of them at NAIRN GRID, the same primary substation. In all, the sites here total 182 MW: 182 MW accepted to connect.
Price what a delay would do to your project
QueueWatch reports what changed in the DNOs' published connection registers. It doesn't tell you what to do about it. That's what QueueQuant is for.
Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.
Get the plan that holds up best for your site, and where that answer flips.
What you get from QueueQuant
- The route to power that wins
- How to size every asset on the site
- The level of delay or curtailment at which that answer flips
- Whether the project is worth building at all
- How bad the worst outcomes get, at the risk level you choose