QueueWatchby QueueQuant Price my project Get the plan that holds up best for your site, and where that answer flips.

DRYNOCH RAAS FACILITY

At DUNVEGAN GRID

SSEN Embedded Capacity Register, October 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Oct 2035
Status
Accepted to connect
Customer
Not stated
Site name
DRYNOCH RAAS FACILITY
Address
DRYNOCH RAAS FACILITY, DRYNOCH PRIMARY, ISLE OF SKYE, HIGHLAND, IV47 8SU
Grid reference
Easting 140526, northing 831212
Licence area
North of Scotland (SHEPD)
Grid supply point
DUNVEGAN GRID
Bulk supply point
Not stated
Primary substation
DRYNOCH
Connection voltage
11 kV
Technology group
Other or not stated
Energy source 1
OTHER, OTHER: 0.001 MW registered
Registered capacity
0.001 MW
Change to maximum export capacity
1.2 MW
Change to maximum import capacity
0 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
15 Mar 2024
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
April 2024 edition

Change history

Tracked since the April 2024 edition, across 31 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 31 Oct 2035 (not stated in the October 2025 edition)

Also at DUNVEGAN GRID

GSP view

3 other sites at this grid supply point in the October 2026 edition. In all, the sites here total 88 MW: 28 MW connected, 60 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose