CLASHINDARROCH WIND FARM 2 - ADDCAP

VATTENFALL WIND POWER LTD at CAIRNFORD

SSEN Embedded Capacity Register, November 2026 edition

Site, company and substation names are shown as they appear in the registers, including capitalisation.

Target energisation date
31 Aug 2026
Status
Accepted to connect
Planning consent
Granted on appeal 26 Jun 2023
Scottish Government (S36), reference ECU00002002 · Source: REPD
Contract for Difference
Allocation Round 6
Customer
VATTENFALL WIND POWER LTD
Site name
CLASHINDARROCH WIND FARM 2 - ADDCAP
Address
CLASHINDARROCH WIND FARM 2, HUNTLY, ABERDEENSHIRE, AB54 4YL
Grid reference
Easting 342767, northing 835445
Licence area
North of Scotland (SHEPD)
Grid supply point
CAIRNFORD
Bulk supply point
Not stated
Primary substation
CAIRNFORD
Connection voltage
33 kV
Technology group
Wind
Energy source 1
WIND, ONSHORE WIND TURBINES: 77 MW registered
Registered capacity
77 MW
Change to maximum export capacity
77 MW
Change to maximum import capacity
2.195 MW
Flexible connection
Not stated
In a connection queue
Not published by SSEN
Date accepted
24 May 2019
Date connected
Not stated
Distribution reinforcement reference
Not published by SSEN
Transmission reinforcement reference
Not published by SSEN
Export MPAN
Not stated
Import MPAN
Not stated
Last updated
10 Feb 2026
Tracked since
August 2023 edition

Change history

Tracked since the August 2023 edition, across 40 editions.

Changes to the details QueueWatch tracks, newest first.

  • November 2025 edition
    Target energisation date stated as 31 Aug 2026 (not stated in the October 2025 edition)

Also at CAIRNFORD

GSP view

3 other sites at this grid supply point in the November 2026 edition, 2 of them at CAIRNFORD, the same primary substation. In all, the sites here total 232 MW: 37 MW connected, 195 MW accepted to connect.

QueueQuant

Price what a delay would do to your project

QueueWatch reports what changed in the DNOs’ published connection registers. It doesn’t tell you what to do about it. That’s what QueueQuant is for.

Give QueueQuant a site and it compares every way you could power it, on the grid or off it: waiting for the firm date, taking a non-firm offer, building a private wire or going off-grid, across every combination of contracted capacity, generation and battery. That’s millions of possible plans, each tested against thousands of possible futures for delay, curtailment and price. It returns the one plan that holds up best, even when that plan is not to build.

Price my project

Get the plan that holds up best for your site, and where that answer flips.

What you get from QueueQuant

  • The route to power that wins
  • How to size every asset on the site
  • The level of delay or curtailment at which that answer flips
  • Whether the project is worth building at all
  • How bad the worst outcomes get, at the risk level you choose

See how we’d price it: Sell now, or wait for your Gate 2 offer?

Planning consent

The planning decision or stage for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition, with the planning authority and its reference. QueueWatch matched the site to that record. The register’s status can lag behind planning decisions, so the two may differ.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.

Contract for Difference

The Contracts for Difference allocation round for this site, from DESNZ’s Renewable Energy Planning Database (REPD), October 2026 edition. QueueWatch matched the site to that record.

How QueueWatch matches projects · Spotted a wrong match? Email info@queuequant.com.